The dismissal of three managers at Sénégal Numérique SA (SENUM SA) has for several weeks pitted the state-owned company’s management against these employees and a collective, the Réseau des Sénégalais pour le numérique et la souveraineté informatique (RNS). In a right of reply published on 15 November, management links the dismissals to PASSANT, a CFA 50 billion fibre-optic network launched in 2019. Here is what we know, what has been established and what remains to be shown.
Key takeaways
- The project: PASSANT, a fibre-optic network awarded in 2019 through an unsolicited bid to the Spanish firm Liteyca, for CFA 50,000,838,369 including taxes, according to the ARCOP audit.
- The official finding: the audit commissioned by ARCOP finds the work « broadly consistent with the studies ». It nevertheless notes a stalled project, penalties that were not applied and « a lack of rigour on the part of SENUM ».
- The accusations: SENUM SA puts the loss at CFA 24 billion, based on a second audit that has not been made public. It has announced three complaints in which it is a civil party.
- The challenge: the dismissed employees and the RNS denounce irregular dismissals and the managing director’s refusal to reinstate them.
A fibre network launched in 2019 and never accepted
In August 2019, the Senegalese government announced the Structural Support Project for the Digital Land-Use Strategy (PASSANT), according to Agence Ecofin, as reported by Osiris. The project was entrusted to the State IT Agency (ADIE), now Sénégal Numérique SA, together with the Spanish company Liteyca S.L. The programme announced included 339.8 km of backbone network, fibre connections for more than 300 government buildings and 125 public Wi-Fi points, at an estimated cost of CFA 50 billion over two years.
The technical audit carried out by the firm ADOC for the Public Procurement Regulatory Authority (ARCOP), dated November 2024, provides more precise data. The contract (reference F 2611/18) was awarded through an « unsolicited bid » for CFA 50,000,838,369 including taxes. It was financed by CBAO and Banco Santander, and the service order is dated 15 January 2019. Planned over 24 months, it was extended twice with no financial impact, by 18 months in January 2021 and then by 15 months in January 2023. The contractual deadline was thus pushed back to 13 April 2024. At the time of the site visits, in April 2024, there had been no provisional acceptance and work had « stopped ».
What the ARCOP report actually says
The report, published on ARCOP’s website, paints a mixed picture. On the one hand, the auditors consider the facilities « broadly consistent with the studies ». On the other, they note a 22-month delay, a stalled project and « a lack of rigour on the part of SENUM ». Three figures stand out:
- Management fees: CFA 4,513,438,738 in management and supervision fees paid at the start, « without any guarantee » on how they would be used.
- Late-delivery penalties: about CFA 5 billion in penalties not applied.
- Work outside the estimate: CFA 69 million of work certified and paid although it was not in the estimate.
The auditors’ opinion describes the execution as « unsatisfactory ». They consider the unit costs of the points of presence (POPs) and the fibre « high » and recommend a detailed study.
The report also contains SENUM’s responses. The company says in particular that some work « was not completed by the subcontractors of the partner Liteyca ». The auditors reply that this work « was accepted and paid for by SENUM ».
This document is at the heart of the dispute, because each side reads it in its own way. In October, the dismissed managers told Seneweb that an earlier ARCOP review had found « overall technical compliance » without naming anyone responsible. Management, by contrast, focuses on the finding of « unsatisfactory » execution and the recommendation for a further study.
A second, unpublished audit behind SENUM’s figures
To follow up on that recommendation, management says it commissioned a second independent technical audit. This report has not been published and SocialNetLink has not been able to consult it. According to the right of reply, it issues « an unfavourable opinion » on the execution of the contract and finds CFA 3.4 billion of non-compliant work out of CFA 6.9 billion of civil engineering work paid for. It adds CFA 17 billion in losses linked to the previous management’s « failure to exercise SENUM’s contractual rights » (start-up advance, performance bond, late-delivery penalties), as well as CFA 3.5 billion in overpricing of civil engineering work.
These three items add up to about CFA 23.9 billion, matching the CFA 24 billion loss put forward by SENUM SA. The company also refers to a 343 km network that is « not operational », costing CFA 19.5 billion, and CFA 19 billion in future losses linked to the depreciation of the infrastructure. These amounts could not be independently verified. They differ sharply from the estimate reported in October by Seneweb, which referred to a loss of « several hundred million CFA francs ».
Three dismissals for gross misconduct, reinstatement refused
According to management, these findings led to the dismissal of three employees for gross misconduct. Two of them had been in technical charge of PASSANT, as « project manager » and « technical coordinator ». The third is accused over the management of fuel for the vehicle fleet. SENUM SA says it complied with labour law, in particular the limitation period and the right to respond through requests for explanation. It states that the project was then run by the former managing director, Cheikh Bakhoum, who was replaced by Isidore Diouf in May 2024.
The employees dispute this account. In October, they told Seneweb they had not been heard on the substance. They said some requests for explanation gave them only 24 hours, and that the contract had been initiated and signed by the former management, with their own role limited to technical supervision. They also said their IT access had been cut and their bank accounts blocked, a claim Seneweb itself said « remains to be verified ».
On 12 November, the RNS revived the case with a statement reported by Dakaractu and then by Osiris. The collective accuses the managing director of refusing « categorically and head-on » the reinstatement requested by the supervising ministry. It mostly uses the conditional. Dakaractu noted that the statement did not include any position from SENUM’s management or the ministry.
Management hits back
On 13 November, several daily newspapers picked up these accusations. On Facebook, Isidore Diouf denounced « coordinated and simultaneous » coverage and a « fringe of the press given to mercenary journalism ». He promised that « the real issue will be addressed in due course ». He provided no evidence of a commissioned campaign, as Xalima pointed out.
The right of reply of 15 November sets out management’s position in detail. SENUM SA says it was not contacted by the media concerned or by the RNS, which it says it does not know. Questioned by the Ministry of Telecommunications and Digital Affairs about compliance with the Labour Code and a request for reinstatement, it says it replied in several letters. In them, it maintains its decision and forwards the audit reports and the assessment of the loss.
According to the same document, the three employees took their case to the labour inspectorate on 11 November 2026. After hearing the parties, the inspectorate reportedly found « that there was no right to reinstatement » and closed the case « with no further action ». Management also says one of the employees tried to physically assault its representative during the hearing, and reserves the right to take legal action. These claims have not been confirmed by the labour inspectorate or by the employees.
The legal front
SENUM SA says it has filed three complaints as a civil party for embezzlement of public funds, fraud involving public funds, forgery and use of forgeries, and breach of trust. Two target the employees linked to PASSANT, the third the one accused over fuel management. The company also says it has referred the matter to the Court of Auditors. It adds that an inquiry by the Criminal Investigation Division (DIC) has been under way since the ARCOP report was published. So far, the judicial authorities have made no statement on these proceedings. Those targeted are presumed innocent.
Beyond the labour dispute, the case raises the question of how the state’s major debt-financed digital projects are monitored. The infrastructure planned under PASSANT was meant to connect hundreds of government buildings to fibre. Seven years after the project was launched, it has still not been accepted.