🇬🇧 English | 🇫🇷 Français
A week after the Youth Olympic Games closed, Mayor Abass Fall presented the City of Dakar’s financial report: just over CFA 23 billion mobilised, including a CFA 5 billion state grant. Artificial-turf pitches, renovated squares, lighting and the decoration of public sites make up the legacy the municipality is claiming.
Key points
- The amount: over CFA 23 billion, of which CFA 18.174 billion from the city and CFA 5 billion from the state.
- The projects: 21 artificial-turf pitches, renovated squares, roads and lighting.
- The tensions: the mayor accuses ONAS and AGETIP of damaging some city works.
- Next: a detailed spending report will be handed to the press.
The City of Dakar on Friday 20 November 2026 presented its report on its role in the Dakar 2026 Youth Olympic Games (YOG), held from 31 October to 13 November. Speaking to the press, Mayor Abass Fall put the municipality’s contribution at more than CFA 23 billion for the first Olympic event ever held on the African continent.
« For everything it has done, the City of Dakar deserves a gold medal, » the mayor said, adding that the capital had « played its part to the very end ». « We worked day and night to achieve these results, » he said, according to remarks reported by Le Populaire.
CFA 18 billion from the city, CFA 5 billion from the state
According to the mayor’s figures, as reported by Le Populaire, the city spent more than CFA 23 billion: CFA 18.174 billion from the municipality, plus a CFA 5 billion grant from the Senegalese state. Abass Fall said he had asked the state for CFA 20 billion, a request that was not met because of the economic situation.
The state grant was earmarked for investment. In September, the city had set out how it would be split: CFA 2 billion for roads, CFA 1 billion for street lighting, CFA 1 billion for branding and CFA 1 billion for boulevards and public squares.
Pitches, squares and lighting
The municipality highlights 21 artificial-turf pitches built across the capital’s districts. Some are still being finished and are due to be opened in the coming days.
In public spaces, the city renovated Place de l’Indépendance and the Allées Cheikh Sidaty Aïdara, and delivered a fully rehabilitated Place de la Nation, the main venue for its celebrations during the Games. Road and lighting works were also carried out, notably in Grand-Dakar and on Boulevard de la Gueule-Tapée.
The city also installed 2,000 waste bins with SONAGED, carried out clearance operations and renovated the municipal radio station. A first water-confidence pool for children has been installed, with 13 planned in Dakar schools.
Beyond Dakar
« The City of Dakar did not limit itself to Dakar, » the mayor said, describing the municipality as « very generous » towards other localities. More than 50 state sites and buildings were decorated and lit, notably in Saly and Diamniadio, the two other YOG hubs.
On the public side, the municipality reports more than 10,000 registered volunteers, three fairs (culinary, institutional and cultural), regattas, the torch relay and the hosting of 50 young Africans. Local artists and graphic designers were involved in dressing the city.
Friction with the state and its agencies
Abass Fall also used the report to point to institutional tensions. He said the city is not a rival to the state and accused ONAS, the sanitation agency, and AGETIP, the public works agency, of damaging or replacing some municipal works, notably on the Corniche Ouest.
A detailed report to come
The mayor said a detailed document on the projects and spending will be handed to the press once finalised. He added that the works were awarded to Senegalese companies.
At the closing ceremony on 13 November, Abass Fall received an award from the International Olympic Committee. He dedicated it to the people of Dakar, calling for the Games’ legacy to be preserved.
Photo: DR
Ne manquez aucune actualite tech et startup
Rejoignez notre chaine WhatsApp et abonnez-vous a SNL TV sur YouTube.
Rejoindre WhatsAppVoir SNL TV sur YouTube
JOJ Dakar 2026 : la Ville de Dakar chiffre sa contribution à plus de 23 milliards FCFA
Senegal: data protection authority rejects Auchan facial recognition, refers complaint against Sen-CSU and Wave to prosecutor
Données personnelles : la CDP refuse la reconnaissance faciale chez Auchan et transmet au procureur une plainte visant Sen-CSU et Wave